So how do you deal with multi-day tile install?
I'm planning on a ledger at the base of the bathroom to start stacking tile up to the ceiling. Then, I'll do the floor, and then the last row of tile at the bottom of the walls.
When I install that last row of tile, how do I use a leveling system if the thinset at the bottom of the tile has already set.
Should I put leveling clips between the ledger board and the first row of tile so they're there when I add the bottom row?
The same scenario would happen if I were up 3 or 4 courses of tile and I had to stop for the day. Do I insert leveling clips on the top edge of the last row and just pick up where I left off the next day?
62 Views


Membrane over drywall..(Greenboard) what’s your thought on going with this shower waterproofing method, I’m considering on control wall of shower, just seems like a faster & easier than using dry/wall to foam board transition, also hydro ban over schluter membrane on shower pan is that recommended ???